Ongoing Projects

Long-Term Plans

Vision Statement: Our Town, Our Vision

Land Use Plan: A Guide for Growth 2012 - 2022

Downtown Master Plan: the plan for the downtown area which is based on seven principles that collectively reinforce the livability of the town center

Composite Bicycle and Pedestrian Plan

Parks and Recreation Master Plan: Evaluated recent changes throughout the community and initiated a public discussion on future park and recreation needs.

Long-Term Projects

Comprehensive Transportation PlanThe Towns of Matthews and Stallings undertook the development of this Transportation Plan together to ensure future plans for the area would support the needs of both Towns. Though the Towns are located in separate counties, residents and commuters share common roads and routes as they travel to work, shopping, recreational activities or visiting family and friends. A dramatic change of a route in Matthews could directly or indirectly affect residents in Stallings. This collaborative effort of the Towns intends to fully understand the travel patterns of all citizens and to develop project recommendations that would benefit the area as a whole.

Current and Pending Projects (as of November 19, 2015)

Below is the current status of the project currently proposed or underway.  Please note that all completion dates are tentative and are highly dependent on weather conditions.

2015 Resurfacing- The contract was awarded to Trull Contracting, LLC for $716,410.75.  The contractor has completed the full-depth reclamation (FDR) and paving in Matthews Estate, West Matthews Street, Oscar Drive area, Independence Pointe Parkway and Windsor Square Drive.  Brigman Road was added to the contract for approximately $73,000 as it will tie into the new entrance to the Sportsplex and was in poor condition and has been completed.  This is a Town-funded project. Except for punch-list items, this project is complete.

Charles Buckley Way- Contract was awarded to Sealand Contractors Corporation for $433,213.07. The contractor has completed the paving and striping.  Our Landscaping Division has installed trees and shrubbery.  Except for a culvert crossing under John Street, this 500 LF project is complete and is currently open to traffic. This is a Town-funded project.

South Trade Street Widening (U-5804A)- The contract was awarded to Sealand Contractors Corporation for $4.2M.  Curb and gutter on one side is complete and they are starting to pave on that side.  Windstream has relocated their utility underground.  Contractor is currently working on the MARA side of the road and installing the Courtney connector road. Current contract completion date is March 2016.  However, this date is likely to be extended due to poor weather.  The contractor will be doing a small amount of work over the next two weeks and will then have to shut down work on the portion of the project within the NCDOT right-of-way due to NCDOT winter restrictions. They will continue with work on the Courtney connector road during the winter. This is a Town-funded project on an NCDOT road.

South Trade Street Culvert (U-5804B)- Due to the new flood plain maps being released and the CLOMAR expiration, this project will have to go back through environmental reviews.  It is anticipated that construction on this project will begin in late 2016.  The Town and County will be responsible for costs associated with running the greenway under South Trade Street plus the associated greenway path.  Current cost estimate for the culvert is $1.3M.  This is an NCDOT project, though the funding to put a pedestrian tunnel under South Trade Street as part of this project will likely be funded with money from NCDOT, Mecklenburg County and the Town.

Talbot Court Extension- This extension is tied to the first building C/O for Plantation Village.  Edifice Builders currently has the retaining wall being designed and then has to get it approved through Mecklenburg County.  Construction of the road is not likely to begin until November 2015 at the earliest and is expected to be complete in the spring of 2016.  This is a privately funded roadway that will be turned over to the Town for maintenance once complete.

McKee Road Extension (U-4713)This project is broken into several segments.   Segment A (U-4713A) of this proposed project will extend McKee Road 4,000 feet from its existing terminus at Pleasant Plains Road to John Street. This section is unfunded with ROW and construction expected beyond 2025. Construction estimate is $6.8M.

Segment BCampus Ridge Road Relocation (U-4713B), will extend it 1,500 feet from John Street to existing Campus Ridge Road. The environmental document can be found here.  An overall schematic of the road can be found here. Contract was awarded to Blythe Development at the June 8, 2015 Board Meeting.  The total construction cost is $1.7M, with the Town contributing $361,456 toward construction and construction oversight.  The rough grading for the project is almost complete.  Project contract completion date is April 2016.

Segments C, D and E are proposed to further extend McKee Road to Independence Boulevard.  Section C, which takes the roadway over the CSX rail line is currently unfunded.  Section D will likely be built with the development of the adjacent property.  Section E will be built as part of the Monroe Expressway project (R-3329/R-2559).

Matthews-Mint Hill Road Superstreet near Butler High School (U-5511)- The contract was awarded to J.T. Russell for $675k.  The Town has committed to $240k of this plus half of any overruns. The remainder of the funding is from a Federal grant given to the Town.  Please note that the multi-use path shown on the conceptual drawing was not able to be constructed due to limited funding. The contractor has installed the storm drainage and begun widening on the south side of the road.  The contract completion date was mid-October 2015 but has been delayed due to the weather and, due to NCDOT winter restrictions, will likely not be completed until April 2016.

Sportsplex-  Located at 1505 Tank Town Road, this project is a $32M athletic complex for field sports and includes adjoining privately held land for a Family Entertainment Complex. The project is being done jointly with the County.  The Town of Matthews has agreed to investing $2M in the project. Phase I of this project is open and includes five multi-purpose fields, a shelter area and a playground built in tribute to the lives lost in the September 11, 2001 terrorist attack. Ultimate build-out includes 12 fields, including a stadium that sits approximately 2,700 people, with the capability of further seating expansion. The contractor is currently grading for phase II. Once complete, there will be a new public roadway connection between Tank Town Road and Brigman Road. Project completion is anticipated to be August 2016.

Greylock Ridge Extension- This proposed 2,200 foot long road will connect John Street to the Sportsplex and Family Entertainment District. The preliminary design for the roadway is done.  No funding has been identified to finalize plans or move toward construction.

Idlewild and Hwy. 51 Roundabout (U-5115)- This project has been fully designed.  It will be constructed in the summer 2016 and will require the closing of the intersection during construction. It was designed for the future widening of NC 51 (U-5007). Construction estimates are around $1.6M. Matthews and Mint Hill are responsible for a combined 20% match ($80k each).

Weddington Road/I-485 Interchange (R-0211EC)- This will add an interchange at Weddington Road and I-485 and will also improve a section of Weddington Road. Funding for ROW is currently in 2017 with construction in 2019-2022.  Due to additional funding from HB 97 in the TIP, the project is now likely to be funded fully from the TIP. There is also a good possibility that it will be built as part of the I-485 Express Lanes (I-5507) project. Project estimate is $20M.  More information about the project can be found on the CRTPO website.

NC 51 Widening (Matthews Township Parkway to Lawyers Road, U-5007)- Widen to multi-lanes. ROW in 2022, construction in 2024. Budget is $35.1M.

NC 51 Widening (Sardis Road to E. John St./Monroe Rd., U-5763)- This project will widen NC 51 from four to six lanes, including a median and a multi-use path).  It is in the planning stages. ROW in 2018 and construction in 2020. Project estimate is $3.9M.

Sam Newell Road Multi-Use Path (Rice Road to Crown Point Elementary, EB-5783)- ROW in 2017, construction in 2018.  Project estimate is $300k, with the Town contributing $60k.

Pleasant Plains Road Bicycle Lanes (Trade St. to McKee Rd., EB-5779)- ROW in 2019, construction in 2020.  Project estimate is $270k. The Town will contribute $54k toward the project.

I-485 Express Lanes (I-5507)- New express lane in each direction from I-77 to US 74. ROW and construction in 2016. Completion in FY 2019. Project estimate is $203M. NCDOT has more information about the project here.

Monroe Expressway (R-3329/R-2559)this $840 million, 19.5 mile project is an all-toll facility from U.S. 74 east of I-485 in Mecklenburg County to U.S. 74 between Wingate and Marshville in Union County. Clearing has been completed east of Hwy. 601 and grading is underway.  They have a tentative completion set for 2018. NCDOT has more information about the project here.  CRTPO has additional information on their website.

US 74 Widening and Express Lanes (U-2509B)- This project is broken into two segments. Segment A proposes express lanes between Conference Drive and Sardis Road North. Segment B proposes express lanes between Sardis Road North and I-485. NCDOT has more information about the project here. The project is currently in the planning stages.  ROW date is 2020.  Construction date is 2022-2025.  Project estimate for section B is $207M, with the total project estimate of $406M.

An additional project (U-5526) proposes to add express lanes on U.S. 74 from I-277 to Wallace Lane, with construction starting in FY 2017. More information about the $17.5 million project can be found here.

Idlewild Road Widening (U-4913)- Widen Idlewild Road from I-485 to Stevens Mill Road. ROW in 2020, construction in 2022.  Project estimate is $7M.

John Street / Old Monroe Road Widening (U-4714)- This widening project is divided into three segments.  Section A is from its intersection with Trade Street in downtown Matthews to I-485. Section B is from I-485 to Waxhaw Indian Trail Road.  Section C is from Waxhaw Indian Trail Road to Wesley Chapel-Stouts Road.

The most recent schedule shows right of way acquisitions for Segments A and B in FY 2020-22, and construction in FY 2022-24, with Segment C unfunded.  The total cost for building these segments is $58.2M, with Segment A estimated at $17.4M.  Due to additional funding from HB 97 in the TIP, all three segments of the project are likely to be funded and built at the same time with right-of-way in 2020 and construction in 2022-2024.

Since the project is receiving federal funds, it is required to have an Environmental Assessment (EA).  As part of the EA, the design team held a Charrette session for initial public input on August 27 through 29, 2013.  More information can be found here:

Opening Night Presentation 
Closing Night Presentation 
Charrette Summary

January 21, 2014 Meeting Summary
Public Meeting Display Boards
Meeting Handout
Meeting Comment Form
NCDOT Superstreet brochure

June 2, 2014 Presentation
John Street Concept drawings- August 2014
John Street Concept drawings- September 2014

Pavement Rehabilitation on I-485 between Idlewild Road and U.S. 74 - Two projects (I-5748 and I-5827) propose to resurface both directions of I-485 in this area. The first project is funded for FY 16 for $500,000 and the second is funded for FY 19 for $3 million.

LYNX Silver Line is a proposed rail line between uptown Charlotte and the Matthews area. CATS is currently conducting a rail alternative analysis and transit study, which extends 13.5 miles from Charlotte’s City Center to the border of Mecklenburg and Union Counties, including the town of Matthews.  The study will define a fixed-rail guideway alignment, provide an interim bus transit strategy that utilized the future Independence Boulevard managed lanes, and develop land development strategies to protect and preserve the fixed guideway alignment. The schedule will culminate with presenting for a vote a Locally Preferred Alternative to the Charlotte Regional Transportation Planning Organization (CRTPO) at their May 2016 meeting.

More information about the study, including maps and a survey for public input can be found at the LYNX Silver Line Web Page.

Future funding for the Silver Line may be hampered by recently passed NC budget that caps the amount NCDOT can fund for a light rail project at $500k

Rice Road Extension is a project to extend existing Rice Road to the existing Rice Road Extension, which accesses Independence Boulevard.  NCDOT has committed to installing a traffic signal at the Rice Road and Sam Newell Drive intersection once this project is completed.  This project is estimated to cost approximately $350k.  Funds for this project have not yet been identified.